This Bid Bulletin is being issued to all prospective bidders to clarify some provisions in the bidding documents for the above reference tender.
The amended description, as follows:
| FROM
| TO
|
| Submission of Elig. Reqts. / Env I & II = 07 Jul 2008 / 8:00-9:00 a.m.
| Submission of Elig. Reqts. / Env I & II = 07 Aug 2008 / 8:00-9:00 a.m.
|
| Opening of Elig. Reqts. / Env I & II = 07 Jul 2008 / 9:00 a.m.
| Opening of Elig. Reqts. / Env I & II = 07 Aug 2008 / 9:00 a.m.
|
| Bid Evaluation & Post-qualification = 08-14 Jul 2008 be the responsibility of the contractor?
| Bid Evaluation & Post-qualification = 08-14 Aug 2008
|
| Notice of Award = 21 July 2008
| Notice of Award = 22 August 2008
|
TERMS OF REFERENCE
| FROM
| TO
|
| 3.0 Exceptions to the Specifications – In the event that the equipment does not meet the requirements of these specifications, or does not include the operational features required, the bidder may take exception to the specification if this is duly noted in the bid and an alternate bid is submitted.
| 3.0 Exceptions to the Specifications – In the event that the equipment does not meet the requirements of these specifications, or does not include the operational features required, the bidder may take exception to the specification if this is duly noted in the bid and a better alternate bid is submitted.
|
| 7.0 Equipment Brochures – the bidders shall include/provide complete set of brochures and indicate in the offer religiously including the model number of respective equipment to be supplied.
| 7.0 Equipment Brochures/Block Diagram – the bidders shall include/provide Engineering block diagram of the whole radar and power supply system including lightning arrester, grounding systems, etc. in standard engineering format with complete set of brochures. Also indicate in the offer religiously the model number, specification of respective equipment to be supplied.
|
Additional Requirements:
II. Terms and Conditions:
* The bidder/supplier shall include in the bid the provision of recommended spare parts;
* The bidder/supplier shall include the list of serviceable parts with corresponding price in foreign currency (Euro or US $) for five (5) years warranty without price increase.
Additional Requirements:
Technical Specifications - Minimum
1.0 Weather Doppler Radar
* 1.10 Modulator shall be full solid state;
* 1.11 Radar data & product shall be in standard format
Power Supply Specifications:
| FROM
| TO
|
| 2.2 Diesel Generator – 25 KVA w/ ATS and micro controller. Air-cooled with day tank capacity for 2 days
| 2.2 Two (2) sets Diesel Generator – 25 KVA w/ ATS and micro controller. Air-cooled with day tank capacity for 2 days
|
| 2.6 Solar Power Supply systems w/ inverter
Construction – solar cell modules shall use poly-crystalline photovoltaic cell technology. Protection – the cells should be encapsulated beneath high-transmission tempered glass. The rear surface should be completely sealed from moisture and mechanical damage by a continuous high-strength polymer sheet. Rated Power – 1 KVA
| 2.6 Solar Power Supply systems w/ inverter
Construction – solar cell modules shall use poly-crystalline photovoltaic cell technology. Protection – the cells should be encapsulated beneath high-transmission tempered glass. The rear surface should be completely sealed from moisture and mechanical damage by a continuous high-strength polymer sheet. Rated Power – 1 KVA and 7 days back-up time
|
* 2.8 Automatic voltage regulator – 25 KVA
This Bid Bulletin is hereby made an integral part of the Bid Documents.
Please be guided accordingly.
FLAVIANA D. HILARIO
Chairman, PAGASA Special BAC